Monday 25 May, 2026:
First thing this morning flagged safety barriers were put up. Soon after 8.30 a/m a bunch of visitors arrived the check out the scene, is what I first thought. Now thinking them the new crew serving the drilling rig, inspecting the platform …

All kinds of excitement this morning. Two new machines from Anora Foundations were trucked in and unloaded … (Took this shot from the sixth floor. The door to the fire escape slipped shut, and lol I had to walk down ten flights of stairs to the podium. Live and learn, as the saying goes.)

Quote from anora.com.au “Specialising in bored piers, retention systems, and micropile installations, Anora supports projects of every calibre and complexity from residential foundations through to Tier 1 commercial and infrastructure projects.”
The blue machine, after it was driven off the semi, made its way to the mysterious shelf built at the front of the site. Here being prepped …

The CAT set to unloading the gear needed to run the drilling machine.

Covered walkways being installed between the cabins.

The drilling rig unfolded …